Purchase & Engineering Timeline | Finishing Systems – GAT

With your site validated and proposal approved, GAT locks in a production slot and publishes a detailed project timeline that charts every task, deliverable and milestone on the road to a fully operational finishing system.

Week‑By‑Week Project Schedule (Typical 28‑Week Cycle)

WeekMilestoneGAT ResponsibilitiesYour Actions
0PO + Deposit ReceivedOpen job number, assign PM & lead engineerIssue purchase order, 30 % deposit
1Kickoff ConferenceReview specs, finalize change log, publish Gantt chartApprove baseline schedule
2–6Detailed Engineering2-D/3-D models, P&IDs, electrical schematicsReturn redlines & approvals
7Design FreezeRelease drawings to fab, order long-lead componentsSign final drawings
8–18Fabrication & Controls ProgrammingBuild washers, ovens, conveyors; program PLC-HMISchedule mid-build visit (optional)
19–21Factory Acceptance Test (FAT)Assemble modules, test-fire burners, verify PLC recipesWitness FAT on-site or via live stream
22–24Crating & ShipmentDisassemble, label, crate; finalize rigging planArrange dock time & insurance
25–28On-Site Installation PrepStage crews, confirm utilities, ship sparesComplete any facility mods

Project Management Tools You’ll Access

Benefits of GAT’s Transparent Timeline

Frequently Asked Questions

Typical terms: 30 % PO, 30 % design freeze, 30 % FAT approval, 10 % shipment.

Change orders are priced and added to the Gantt chart with adjusted ship dates before work proceeds.

Yes—overtime shifts and parallel fabrication can compress the schedule if critical parts are available.

Ready to Lock Your Production Slot?